Renovation Building 780, Department of Navy, Millington, Tennessee – Replace Sanitary Sewer – $334K


Project consisted of repairing sanitary sewer line feeds and manholes. Lined manholes with C.I.P.P. to prevent corrosion and root growth intrusion.

Installed new factory sewer manhole ring and iron cover with sanitary sewer cast into the top of the cover. Completed all work concrete and brick work necessary to the top of the manhole allow for proper installation of the manhole ring and cover.Spray line manhole 5001 with epoxy liner. Furnished and installed cured in place pipe C.I.P.P. Provide necessary repair and replacement of missing brick and cement work to manholes for the raising of the height of the ring and cover above grade. Sprayed line the manhole with epoxy sealant to stop infiltrations.